Joint facilities project #1754
An inspection of the Dam conducted in Fiscal Year 2016 identified surface wear on the exterior face of the San Dieguito Dam that requires refurbishment. This is a preventative maintenance project that includes the design and construction work required to repair the concrete surface in the areas identified. Design was initiated in Fiscal Year 2017 and completed in Fiscal Year 2020. Construction is scheduled to occur in Fiscal Year 2021.
Total Project Cost: $492,700
Construction Cost: $296,875
FY 21 Expenditures: $417,000